Only 2 days out from opening the river back up. And yes, they still have a long way to go before the project is complete. After the river opening, the next big event will be the setting of the girders that span the river.
Today was a day for crews to take care of some of the loose ends.
I decided to stop adding updated images to the update post as, at the current level of over 800 images, it was getting cumbersome for the system to render.
Having said that, if you’re still interested in this project, check out the other postings leading up to this part of the demolition/build by clicking the following link:
Arlington Avenue Bridges Project Links